Project Number: 1499-02
From Milepost: 11.2 To Milepost:11.9
RATA/CAPP funds: $ 985,500
Design Software: Eagle Point
Completed: 2007
The project replaced three substandard 25 mph curves with one 50 mph curve eliminating the need for 4 warning signs. This involved excavating approximately 26,000 cubic yards of gravel material and using it for structural fill and gravel base. The new roadway section has a 24-foot travelled way and two 5-foot shoulders for a total paved width of 34-feet.
A 2350-foot radius horizontal curve was used to keep the affected wetland area under 0.5-acre to expedite the permitting process. A 20-foot wide low profile arch was used to replace two 3-foot diameter culverts that were fish passage barriers.